(Updated on January 25, 2022 from the announcement on January 24, 2022)

Due to the shortage of parts supply caused by the spread of COVID-19 at our supplier in Japan, on January 21 we announced additional suspensions of domestic plant production for completed vehicles (Adjustments to Domestic Production in January) and also our revised production plan for February (Production Plans in February 2022) due to the shortage of semiconductor-related parts.

Today, Toyota announces additional suspensions of domestic plant production for completed vehicles.

With regard to February, as the parts scheduled to be used during the January suspension can now be used in February, some plants and lines originally scheduled to be suspended in the month will now operate. We will continue to make our maximum efforts to deliver as many vehicles as possible to our customers at the earliest possible date.

We sincerely apologize for the inconvenience this may cause to our customers and suppliers due to these changes.

Production suspension after January 25 (Tue) (19 lines in 11 plants out of 28 lines in 14 plants)

Plants Period of production suspension Production vehicle
Toyota Motor Corporation
Motomachi Plant
Production line #1 25 (Tue), 26 (Wed), 27 (Thu), 28 (Fri), 31 (Mon) Crown, Noah, Voxy, Mirai
Production line for GR models GR Yaris
Production line for low volume models LC
Toyota Motor Corporation
Takaoka Plant
Production line #1 Corolla, Corolla Touring, Corolla Cross
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 Prius, Prius PHV, Corolla
Production line #2 Corolla Sport, Camry, ES
Toyota Motor Corporation
Tahara Plant
Production line #1 Land Cruiser Prado, GX, 4Runner
Production line #3 LS, IS, RC, RC F, NX
Toyota Motor East Japan
Iwate Plant
Production line #1 C-HR, Aqua
Production line #2 Yaris, Yaris Cross, Aqua
Toyota Motor East Japan
Miyagi Ohira Plant
Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body
Fujimatsu Plant
Production line #1 Land Cruiser 70
Production line #2 Noah, Voxy
Toyota Auto Body
Inabe Plant
Production line #1 Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body
Yoshiwara Plant
Production line #1 LX, Land Cruiser 300
Production line #2 Land Cruiser 70
Gifu Auto Body Production line #1 Hiace / Ambulance, Granace
Production line #2 Coaster
Hino Motors, Ltd.
Hamura Plant
Production line #1 Land Cruiser Prado, FJ Cruiser

Production suspension in February (7 lines in 6 plants (previously announced as 11 lines in 8 plants) out of 28 lines in 14 plants)

The strike-through lines have been changed to "Operation".
Plants Period of production suspension Production vehicles
Toyota Motor Corporation
Motomachi Plant
GR line 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 14 (Mon), 15 (Tue), 16 (Wed) GR Yaris
Toyota Motor Corporation
Takaoka Plant
Production line #1 12 (Sat), 19 (Sat) Corolla, Corolla Touring, Corolla Cross
Production line #2 12 (Sat), 19 (Sat) RAV4, Harrier
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 12 (Sat), 19 (Sat) Prius, Prius PHV, Corolla
Production line #2 12 (Sat), 19 (Sat) Corolla Sport, Camry, ES
Toyota Motor Corporation
Tahara Plant
Production line #3 4 (Fri), 11 (Fri), 12 (Sat), 19 (Sat) LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 2 (Wed), 3 (Thu), 4 (Fri), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 17 (Thu), 18 (Fri), 19 (Sat) NX, NX PHV, CT, UX, UX300e
Toyota Motor East Japan
Iwate Plant
Production line #1 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 14 (Mon) C-HR, Aqua
Production line #2 Yaris, Yaris Cross, Aqua
Toyota Motor East Japan
Miyagi Ohira Plant
1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 12 (Sat) Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body
Fujimatsu Plant
Production line #2 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 11 (Fri), 12 (Sat), 14 (Mon), 15 (Tue), 16 (Wed) Noah, Voxy

RELATED CONTENT