We at Toyota would like to again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.

We have decided to suspend operations at some of our domestic plants from June 17 (Friday) due to low attendance caused by a COVID-19 outbreak at one of our suppliers, and a shortage of parts supply caused by a production equipment defect at another supplier. The suspension plan this time is in addition to the recent announcement (Adjustments to domestic production in June).

As a result of those suspensions, the number of units affected will be approximately 40,000 and the global production plan for June is revised to be approximately 750,000 units from the original plan (approx. 800,000 units). The production forecast for the fiscal year remains unchanged (approx. 9.7 million).

The global production plan for July will be announced at a later date.

As it remains difficult to look ahead due to the shortage of semiconductors and the spread of COVID-19, there is a possibility that the production plan may be lower. However, we will examine the parts supply closely to minimize sudden decreases in production, and continue to make every effort possible to deliver as many vehicles to our customers at the earliest date.

The following is the suspension schedule of domestic operations in June and July.

Suspension of production in June and July (11 lines in 7 plants out of 28 lines in 14 plants)

Plants Period of production suspension (Announced on May 27) Period of production suspension Production vehicle
Toyota Motor Corporation
Motomachi Plant
Production line #1 June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) June 17 (Fri)*1, 20 (Mon), 21 (Tue), 22 (Wed), 23 (Thu), 24 (Fri), 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) Crown, Noah, Voxy, MIRAI, bZ4X
Production line for GR models GR Yaris
Production line for low volume models June 20 (Mon), 21 (Tue), 22 (Wed), 23 (Thu), 24 (Fri), 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) LC
Toyota Motor Corporation
Takaoka Plant
Production line #1 June 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) Corolla, Corolla Cross, Corolla Touring
Production line #2 June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri), 4 (Mon), 5 (Tue), 6 (Wed), 7 (Thu), 8 (Fri) RAV4, Harrier
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 Prius, Prius PHV, Corolla
Toyota Motor Corporation
Tahara Plant
Production line #1 Land Cruiser Prado, GX, 4Runner
Production line #3 June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 June 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) NX, NX450h+, CT, UX, UX300e
Production line #2 ES, RX
Toyota Motor East Japan
Iwate Plant
Production line #1 June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) Aqua, C-HR
Production line #2 Aqua, Yaris, Yaris Cross
Toyota Motor East Japan
Miyagi Ohira Plant
June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body
Fujimatsu Plant
Production line #2 Noah, Voxy
Toyota Auto Body
Inabe Plant
Production line #1 June 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body
Yoshiwara Plant
Production line #1 June 27 (Mon), 28 (Tue), 29 (Wed), 30 (Thu), July 1 (Fri) LX, Land Cruiser 300
Production line #2 Land Cruiser 70
Daihatsu Motor Corporation
Kyoto (Oyamazaki) Plant*2
June 1 (Wed), 2 (Thu), 3 (Fri), 6 (Mon), 7 (Tue), 8 (Wed), 9 (Thu), 10 (Fri) Probox
Note
*1 Production suspension for the second shift only
*2 Daihatsu Kyoto (Oyamazaki) single shift operation