Toyota would like to extend its sincere sympathy to those affected by the earthquakes that occurred on February 13 (Sat), and hope for the earliest possible recovery of the affected areas.

Due to the effects of the earthquake, adjustments will be made to production operations of plants for completed vehicles in Japan as follows.

We sincerely apologize for the inconvenience caused to our suppliers and people in those regions, due to these changes.

Production suspension for 14 production lines at nine plants (Among a total of 28 lines at 14 plants)

Plant Period of production suspension
(February)
Production Vehicle
Toyota Motor Corporation
Takaoka Plant
Production line #2 18 (Thu), 19 (Fri), 20 (Sat) Harrier, Prius α, RAV4
Toyota Motor Corporation
Tahara Plant
Production line #1 Prado, GX, 4Runner
Production line #3 17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat) LS, IS, RC, NX
Toyota Motor Kyushu Co., Ltd.
Miyata Plant
Production line #1 19 (Fri) 2nd shift, 20 (Sat) NX, UX, CT
Production line #2 20 (Sat) ES, RX
Toyota Motor East Japan, Inc. (TMEJ)
Iwate Plant
Production line #1 18 (Thu) 2nd shift, 19 (Fri), 20 (Sat) C-HR, Aqua
Toyota Auto Body Co., Ltd.
Fujimatsu Plant
Production line #1 17 (Wed) 2nd shift, 18 (Thu), 19 (Fri), 20 (Sat) LC70
Toyota Auto Body Co., Ltd.
Yoshiwara Plant
Production line #1 LC200/LX
Production line #2 LC70
Gifu Auto Body Co., Ltd. Production line #2 18 (Thu), 19 (Fri), 20 (Sat) Coaster
Toyota Industries Corporation Production line #301 17 (Wed), 18 (Thu), 19 (Fri), 20 (Sat) RAV4
Production line #302
Hino Motors, Ltd.
Hamura Plant
Production line #1 18 (Thu), 19 (Fri), 20 (Sat) Land Cruiser Prado, FJ Cruiser
Production line #2 Dyna
Notes
  • Line #2 at Gifu Auto Body operates at one shift.
  • 1st shift only for February 20 (Sat).