We at Toyota would like to once again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, which has caused considerable inconvenience to our customers, suppliers and other parties concerned.

Due to the impact of the semiconductor shortage, we announced our revised production plan for May ("May Production Plan"). However, as a result of the lockdown in Shanghai, China, we have decided to additionally suspend operations of 14 lines at 8 plants in Japan from May 16 (Mon) to May 21 (Sat). (Please see following chart for details)

We had announced that our global production plan for May would be approximately 750,000 units, but due to the impact of the lockdown, it is expected to be around 700,000 units.

The shortage of semiconductors, spread of COVID-19 and other factors are making it difficult to look several months ahead. Still, we will continue to make maximum efforts to deliver as many vehicles as possible to our customers at the earliest possible date.

The following is the suspension schedule of domestic operations in May due to plan revisions.

Production suspension in May (20 lines at 12 plants of the total 28 lines at 14 plants)

Plants Period of production suspension
(Announced on April 18)
Period of production suspension
(Announced on May 10)
Production vehicles
Toyota Motor Corporation
Motomachi Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) Crown, Noah, Voxy, MIRAI, bZ4X
Production line for GR models GR Yaris
Production line for low volume models LC
Production line for Century Century
Toyota Motor Corporation
Takaoka Plant
Production line #1 May 9 (Mon), 20 (Fri) Corolla, Corolla Cross, Corolla Touring
Production line #2 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) Harrier, RAV4
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 May 9 (Mon), 20 (Fri) Prius, Prius PHEV, Corolla
Toyota Motor Corporation
Tahara Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) Land Cruiser Prado, GX, 4Runner
Production line #3 May 12 (Thu) May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 May 9 (Mon), 10 (Tue), 13 (Fri), 16 (Mon), 20 (Fri), 23 (Mon) May 17 (Tue), 18 (Wed), 19 (Thu) NX, NX PHEV, CT, UX, UX BEV
Production line #2 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) ES, RX
Toyota Motor East Japan
Iwate Plant
Production line #1 May 9 (Mon), 10 (Tue), 11 (Wed) C-HR, Aqua
Toyota Auto Body
Fujimatsu Plant
Production line #2 May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu), 13 (Fri), 16 (Mon) Noah, Voxy
Toyota Auto Body
Inabe Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body
Yoshiwara Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri), 21 (Sat)*1 LX, Land Cruiser 300
Production line #2 Land Cruiser 70
Gifu Auto Body Production line #2 May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu) May 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) Coaster
Toyota Industries Corporation Production line #301 May 21 (Sat), 28 (Sat)*1 RAV4
Production line #302 May 16 (Mon), 17 (Tue) RAV4, RAV4 PHEV
Daihatsu Motor Corporation
Kyoto (Oyamazaki) Plant*2
May 18 (Wed), 19 (Thu) Probox
*1 Single shift operation on Saturdays
*2 Single shift operation at the Daihatsu Kyoto (Oyamazaki) Plant