We at Toyota would like to again apologize for the repeated adjustments to our production plans due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers, suppliers, and other parties concerned.

The global production plan for June is approximately 850,000 units (250,000 units in Japan and 600,000 units overseas). Due to the impact of semiconductor shortages, we have adjusted our production plan by tens of thousands of units globally from the number provided to our suppliers at the beginning of the year.

The average global production plan from June through August is around 850,000 units, and 9.7 million units for the full period of fiscal year 2023. The shortage of semiconductors, spread of COVID-19 and other factors are making it difficult to look ahead, but we will continue to make every effort possible to deliver as many vehicles to our customers at the earliest date.

Due to parts supply shortages caused by the lockdown in Shanghai, we have decided to suspend operations in May and in June. The following is the suspension schedule of domestic operations in May and in June.

Suspension of production in May and in June (16 lines in 10 plants out of 28 lines in 14 plants)

Plants Period of production suspension
(Announced)
Production suspension Production vehicle
Toyota Motor Corporation
Motomachi Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) May 25 (Wed), 26 (Thu), 27 (Fri) Crown, Noah, Voxy, MIRAI, bZ4X
Production line for GR models GR Yaris
Production line for low volume models LC
Production line for Century Century
Toyota Motor Corporation
Takaoka Plant
Production line #1 May 9 (Mon), 20 (Fri) May 25 (Wed), 26 (Thu), 27 (Fri), June 2 (Thu), 3 (Fri) Corolla, Corolla Touring, Corolla Cross
Production line #2 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) May 25 (Wed), 26 (Thu), 27 (Fri) RAV4, Harrier
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 May 9 (Mon), 20 (Fri) Prius, Prius PHV, Corolla
Toyota Motor Corporation
Tahara Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) May 25 (Wed), 26 (Thu), 27 (Fri) Land Cruiser Prado, GX, 4Runner
Production line #3 May 12 (Thu), 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 May 9 (Mon), 10 (Tue), 13 (Fri), 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri), 23 (Mon) June 2 (Thu), 3 (Fri) NX, NX450h+, CT, UX, UX300e
Production line #2 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) ES, RX
Toyota Motor East Japan
Iwate Plant
Production line #1 May 9 (Mon), 10 (Tue), 11 (Wed) June 1 (Wed), 2 (Thu), 3 (Fri) Aqua, C-HR
Toyota Motor East Japan
Miyagi Ohira Plant
Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN Taxi
Toyota Auto Body
Fujimatsu Plant
Production line #1 May 28 (Sat)*1 Land Cruiser 70
Production line #2 May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu), 13 (Fri), 16 (Mon) Noah, Voxy
Toyota Auto Body
Inabe Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri) May 25 (Wed), 26 (Thu), 27 (Fri) Hiace, Granace, Alphard, Vellfire, LM
Toyota Auto Body
Yoshiwara Plant
Production line #1 May 16 (Mon), 17 (Tue), 18 (Wed), 19 (Thu), 20 (Fri), 21 (Sat)*1 May 25 (Wed), 26 (Thu), 27 (Fri), 28 (Sat)*1 LX, Land Cruiser 300
Production line #2 Land Cruiser 70
Gifu Auto Body Production line #2 May 9 (Mon), 10 (Tue), 11 (Wed), 12 (Thu), 18 (Wed), 19 (Thu), 20 (Fri) Coaster
Toyota Industries Corporation Production line #301 May 19 (Thu)*2, 21 (Sat), 28 (Sat)*1 RAV4
Production line #302 May 16 (Mon), 17 (Tue), 19 (Thu)*2, 21 (Sat), 28 (Sat)*1 RAV4, RAV4 PHV
Daihatsu Motor Corporation
Kyoto (Oyamazaki) Plant*3
May 18 (Wed), 19 (Thu) June 1 (Wed), 2 (Thu), 3 (Fri) Probox
*1 Single shift operation on Saturday
*2 Operation was suspended for the 1st shift on May 19 due to a lack of parts supply following the water leakage at the Meiji Yosui Toshuko dam.
*3 Daihatsu Kyoto (Oyamazaki) Plant is a single shift operation