We at Toyota would like to again apologize for the repeated adjustments to our production plan due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers, who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.

Due to the impact of the semiconductor shortage, we announced adjustments to domestic production in October ("October Production Plan"). However, we have decided to make additional suspensions of operations at some plants and lines in Japan. The global production volume affected by this decision is approximately 50,000 units (including 25,000 units in Japan), and although we announced global production plan for October was approximately 800,000 units, it is expected to be around 750,000 units by this decision.

The production forecast for the fiscal year remains unchanged at approx. 9.7 million.

The following is the revised domestic operations suspension schedule for October.

Suspension of production in October (5 lines in 5 plants out of 28 lines in 14 plants)

Plant Period of production suspension (Announced on September 22) Period of production suspension (Announced this time) Production model
Toyota Motor Corporation
Motomachi Plant
Production line for GR models October 3 (Mon), 4 (Tue) GR Yaris
Toyota Motor Corporation
Takaoka Plant
Production line #2 October 7 (Fri), 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu) RAV4, Harrier
Toyota Motor Corporation
Tsutsumi Plant
Production line #1 October 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat) Prius, Prius PHV, Corolla
Production line #2 October 8 (Sat), 15 (Sat) Corolla Sport, Camry, Crown
Toyota Motor Corporation
Tahara Plant
Production line #1 October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) Land Cruiser Prado, Lexus GX, 4Runner
Production line #3 October 6 (Thu), 7 (Fri), 8 (Sat), 14 (Fri), 15 (Sat) Lexus LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 October 8 (Sat), 15 (Sat) Lexus NX, NX450h+, ES, CT, UX, UX300e
Production line #2 October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) Lexus ES, RX
Toyota Auto Body
Inabe Plant
Production line #1 October 15 (Sat) Hiace, Granace, Alphard, Vellfire, Lexus LM
Toyota Industries Corporation Production line #301 October 8 (Sat), 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 14 (Fri), 15 (Sat), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu), 21 (Fri) RAV4
Production line #302 RAV4, RAV4 PHV
Hino Motors, Ltd.
Hamura Plant
Production line #1 October 6 (Thu), 7 (Fri), 14 (Fri), 21 (Fri), 28 (Fri) October 10 (Mon), 11 (Tue), 12 (Wed), 13 (Thu), 17 (Mon), 18 (Tue), 19 (Wed), 20 (Thu) Land Cruiser Prado, FJ Cruiser
In the above schedule, it is a single-shift operation on Saturdays.