We at Toyota would like to again apologize for the repeated adjustments to our production plan due to the parts shortage resulting from the spread of COVID-19, and for causing considerable inconvenience to our customers, who have been waiting for the delivery of vehicles, suppliers, and other parties concerned.

Due to the impact of semiconductor shortages, the planned global production volume for November is expected to be approximately 800,000 units (approx. 250,000 units in Japan and 550,000 units overseas).

As a result of this plan, the full-year production forecast for FY2023 is expected to be lower than the previous forecast of 9.7 million units.

It remains difficult to look ahead due to the impact of semiconductor parts and other factors. However, we will continue to closely examine the supply of parts and work with related parties to consider all possible measures to ensure that we can deliver as many vehicles as possible to our customers at the earliest possible date.

The following is the revised domestic operations suspension schedule for November.

Suspension of production in November (11 lines in 8 plants out of 28 lines in 14 plants)

Plant Period of production suspension Production model
Toyota Motor Corporation
Takaoka Plant
Production line #1 November 2 (Wed), 3 (Thu), 4 (Fri), 5 (Sat) Corolla, Corolla Cross, Corolla Touring
Production line #2 November 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 5 (Sat) RAV4, Harrier
Toyota Motor Corporation
Tsutsumi Plant
Production line #2 November 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 5 (Sat), 12 (Sat) Corolla Sport, Camry, Crown
Toyota Motor Corporation
Tahara Plant
Production line #1 November 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 5 (Sat) Land Cruiser Prado, Lexus GX, 4Runner
Production line #3 Lexus LS, IS, RC, RC F, NX
Toyota Motor Kyushu
Miyata Plant
Production line #1 November 5 (Sat), 12 (Sat) Lexus NX, NX450h+, ES, UX, UX300e
Production line #2 Lexus ES, RX
Toyota Motor East Japan
Iwate Plant
Production line #2 November 1 (Tue), 2 (Wed), 3 (Thu), 5 (Sat) Yaris, Yaris Cross
Toyota Motor East Japan
Miyagi Ohira Plant
November 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 5 (Sat) Yaris Cross, Sienta, Corolla Axio, Corolla Fielder, JPN TAXI
Toyota Auto Body
Fujimatsu Plant
Production line #2 November 1 (Tue), 2 (Wed), 3 (Thu), 4 (Fri), 7 (Mon), 8 (Tue), 9 (Wed), 10 (Thu), 12 (Sat) Noah, Voxy
Hino Motors, Ltd.
Hamura Plant
Production line #1 November 3 (Thu), 4 (Fri) Land Cruiser Prado, FJ Cruiser
In the above schedule, it is a single-shift operation on Saturdays.